LEAD TIME CONTROL
Steel Stamping Die | Casting Stamping Die | |||||
Lead time | Small dies ( ≦ 1 M ) Weeks | Medium dies ( 2 M-3M ) Weeks | Big dies (3M- ) Weeks | small dies ≦2000 mm weeks | medium dies 2000-3000mm weeks | big dies ≥3000mm weeks |
Simulation |
2 -3.5 wks |
3.5 -5.5 wks |
5.5 wks |
2 -3.5 wks |
3.5 -5.5 wks |
6 wks |
Design | ||||||
Pattern |
|
|
| 0.5 wks | 0.5 wks | 1 wks |
Casting/steel | 0.5 -1 wks | 1 wks | 1.5 wks | 3 weeks | 4 weeks | 4 wks |
Manufacturing |
2.5 -3.5 wks |
3.5 -5.5 wks |
7 wks |
2.5 -4 wks |
3.5 - 5.5 wks |
7 wks |
Heat treatment | ||||||
Assembly |
3 - 4 wks |
5 - 10 wks |
10 wks |
3 - 4 wks |
5 - 10 wks |
10 wks |
Laser cut parts | ||||||
Off tool parts | ||||||
OK Parts | ||||||
Buy off | ||||||
Total |
8 -12 wks |
13 -22 wks |
24 wks |
11 -15 wks |
16.5 -25.5 wks |
28 wks |
Parallel Management
Parallel between 1、quotation and strip layout 2、strip layout and die design 3、draw die in advance 4、die design and purchasing material 5、pattern and die design 6、design releasing and programming 7、design releasing and machining 8、machining and assembly 9、Q-loop and material purchasing | ![]() |